google-site-verification: googlee16c7726ecc34510.html

Road Construction Updates

Road Construction Updates
Posted on 05/08/2026
Aerial view of a road and intersection in Aurora

As the city of Aurora improves its infrastructure offerings to its current and future residents, demands for more infrastructure, improvements and repairs also grow. On any given work day, there can be as many as 100 active work zones within the city.

Traffic engineering staff make every effort to minimize the impact of these work zones to the traveling public. In addition to reviewing and approving the plans to ensure they are safe and compliant with all regulations, staff also work with contractors to seek alternatives to street closures and minimize the number of lane closures and their duration. Staff also try to keep conflicting work zones from overlapping in time or space. In most cases, these efforts are successful. However, on occasion, alternatives are not available and since we are dealing with the outdoor environment, even the best planned projects get delayed by weather, special events or unknown conditions, resulting in confusion and/or unplanned congestion.

Sign up now for weekly construction updates delivered directly to your inbox via Road Construction Roundup.

Interactive map available
The city has an online map that shows work happening throughout the city that may impact travel on roadways. The map captures annual street maintenance work, transportation projects, public and private utility work, and development projects impacting roadways. Visit this link to view the map.


Annual Street Maintenance Work

See the Weekly Roadwork Construction Schedule

Visit this link
 for more information about city of Aurora roadwork.


Other Road Construction Work (weather delays may be expected for all work zones) 

Please note: Although the city informs online mapping services about our road closures and designated detours/alternate routes, the routes they provide to the general traveling public are generally the shortest or quickest routes between two points. That results in drivers sometimes not following the city's designated detour/alternate routes.

In-progress and due-to-start Projects

56th Avenue lane closures
Westbound East 56th Avenue between North Lisbon Street and North Himalaya Road will have one lane closed to through traffic weekdays only from 8:30 a.m. to 3:30 p.m. from May 7 to 13 due to a private project to install new infrastructure.

Abilene full closure
Both directions of Abilene Street at 33rd Place will be fully closed around the clock from May 18 to 22 due to a city water project to maintain infrastructure.

Center full closure at Nome
Both directions of Center Avenue between Nome and Peoria streets will be fully closed from 8:30 a.m. to 3:30 p.m. daily through May 30 due to a city project to maintain infrastructure. The alternate route uses Exposition between Nome and Oswego. Plan for delays.

Center full closure at Chambers
Both directions of Center Avenue between Chambers Road and East Centrepoint Drive will be fully closed around the clock from May 11 to 19 due to a private developer installing new utilities. The alternate route will use East Alameda Parkway or Exposition Avenue between Chambers and Sable.

Colfax BRT Project: Colfax and Havana lane closures
Both directions of Colfax Avenue at Havana Street will have lane closures around the clock through June 22 due to the installation of new infrastructure related to the East Colfax Bus Rapid Transit Project.

Del Mar Circle lane narrowing
Both directions of Del Mar Circle at Peoria Street will have all lanes narrowed around the clock through May 15 due to a city water project to maintain infrastructure.

Gartrell lane shift
Both directions of Gartrell Road between Aurora Parkway and East Dry Creek Road will have one lane shifted left around the clock from May 18 to July 2027 due to a city project constructing enhanced traffic flow.

Gun Club full closure
All directions of Gun Club Road between Fifth and 10th avenues will be fully closed around the clock from June 1 to 20 due to work to perform utility tie-ins. The alternate route will use Picadilly Road between Colfax Avenue and Stephen D. Hogan Parkway. View detour map.

North Gun Club lane closure
Eastbound North Gun Club Road between East 10th and East 14th avenues will have one lane closed to through traffic from 8:30 a.m. to 3:30 p.m. weekdays only from May 18 to 29 due to a private project to install new infrastructure.

Havana lane closure
Northbound Havana Street between East 19th Avenue and East Montview Boulevard will have one lane closed to through traffic from 8:30 a.m. to 3:30 p.m. weekdays only through May 15 due to a city water project to maintain utilities.

Hoffman lane closures
Both directions of Hoffman Boulevard between Del Mar Circle and Yuba Street will have intermittent lane closures around the clock through May 30 due to a city project to maintain infrastructure. Use alternate route; expect slow traffic.

Jackson Gap lane closure (north of 56th)
Northbound Jackson Gap Street north of East 56th Avenue will have one lane closed to through traffic from 8:30 a.m. to 3:30 p.m. weekdays only through May 21 due to a private project to install new infrastructure.

Jackson Gap lane closures (56th to 64th)
Both directions of North Jackson Gap Way between East 56th Avenue and East 64th Avenue will have two lanes closed to through traffic weekdays only from 8:30 a.m. to 3:30 p.m. May 11 to 13 due to a private project to maintain utilities.

Jackson Gap lane closures (64th to 68th)
Both directions of Jackson Gap Street between 64th and 68th avenues will have two lanes closed to through traffic around the clock from May 13 to 31 due to a private project to perform work to maintain utilities.

Lewiston lane closures
Both directions of South Lewiston Way, north of East Arapahoe Road, will have intermittent lane closures from 8:30 a.m. to 3:30 p.m. weekdays only from May 13 to 26 due to a private utility performing work to install new utilities.

Picadilly full closure
Both directions of Picadilly Road between Stephen D. Hogan Parkway and Seventh Avenue will be fully closed around the clock from May 11 to 30 due to utility tie-in work. The alternate route will use parallel streets; specifically, Gun Club Road between Colfax Avenue and Stephen D. Hogan Parkway. View detour map.

Quincy lane closure (at Himalaya)
Eastbound Quincy Avenue between Himalaya Street and Copperleaf Boulevard will have one lane closed weekdays only from 8:30 a.m. to 3:30 p.m. through May 29 due to work to install new infrastructure.

Quincy turn lane closure (between Parker and Smoky Hill)
Westbound Quincy Avenue between Parker and Smoky Hill roads will have one right turn lane closed around the clock through May 23 due to a city project working to improve intersections. The alternate route will use Hampden Avenue.
 
Smith Road full closure
Both directions of Smith Road between Gun Club Road and Powhaton Road will be fully closed around the clock through May 31 due to a private developer installing new infrastructure. Follow the signed detour route. 

Tower through lanes closed
Both directions of Tower Road at Smith Road will have through lanes closed weekdays only from 8:30 a.m. to 3:30 p.m. through Aug. 27 due to work to maintain utilities.

Tower lane closures near Hampden
Southbound Tower Road south of Hampden Avenue will have two lanes closed around the clock through May 20 due to a city water project for emergency repairs.


Parker/Quincy/Smoky Hill Intersection Improvements Project

Construction of the Parker/Quincy/Smoky Hill Intersection Improvement Project has begun and will continue through at least December 2026, with additional time built in to ensure the project is completed safely and successfully.

Construction activity will start at 7:30 a.m. and end at 5:30 p.m. Monday through Friday, with lane closures from 8:30 a.m. to 3:30 p.m.

Travel Impacts for Monday, May 11, to Friday, May 15 (lane closures will not occur simultaneously)
-Southbound right lane closure on Parker Road just south of Atchison Way and continuing to just south of Rice Place
-Westbound lane closure on Quincy Avenue from Atchinson Way around the clock for the entire week
-Eastbound right lane closure on Quincy Avenue from Parker Road

Project update: Silva Construction is currently wrapping up Phase 1A of the Parker-Quincy-Smoky Hill Intersection Improvements Project, which primarily consists of sidewalk improvements along South Parker Road.

Significant progress has been made throughout this phase, including the full completion of Retaining Wall A. Remaining Phase 1A activities include final sidewalk placement, asphalt paving at parking lot entrances and adjacent parking areas, and final parking lot striping. At this time, Silva Construction anticipates these improvements will be fully completed by next week, weather permitting.

In addition to the South Parker Road improvements, substantial sidewalk operations have progressed along North Quincy Avenue from Smoky Hill Road westbound toward Parker Road. Most of the sidewalk within this corridor has been poured and continues to advance toward completion.

The new intersection improvements will reduce congestion, improve traffic flow, and increase pedestrian safety in this area. This project is designed to improve safety for pedestrians and the traveling public. 

Visit the project webpage to view weekly travel impacts.


56th and Hudson Road Closures and Project

(view map for aerial view of closure impacts and alternate routes)

Please note: Flood damage has restricted access to both 56th Avenue and Hudson Road. Heavy rainfall undermined the roadways and destroyed the road surface in some locations. The road closures are necessary to protect the traveling public while the project team works to reopen the roadways. Project information will continue to be posted on the project webpage as it becomes available.

-56th Avenue between Monaghan and Hudson
Both directions of 56th Avenue between Monaghan and Hudson roads are fully closed around the clock due to extensive road damage. The replacement road is currently being designed, and construction is now estimated to start in late fall 2026. Follow the signed detour; use alternate routes. The detour route uses Monaghan Road or Imboden Road between 26th Avenue and 56th Avenue.
-Hudson Road between 56th Avenue and 26th Avenue
Both directions of Hudson Road between 56th and 26th avenues are fully closed around the clock due to extensive road damage. The replacement road is currently being designed, and construction is now estimated to start in late fall 2026. Follow the signed detour; use alternate routes. The detour route will use Monaghan Road or Imboden Road between 26th and 56th avenues.


I-70 Picadilly Interchange now open

The city of Aurora’s new diverging diamond interchange (DDI) at I-70 and Picadilly Road is now open to all lanes of travel in all directions for vehicle traffic. The newly constructed Picadilly Road from East 19th Avenue to Smith Road is also open, along with the new bike and pedestrian pathways. 

As you drive through the interchange, please pay attention to new overhead signs, as on- and off-ramp descriptions may have changed. 
 
Continuing Traffic Impacts
-Daytime various alternating right- and left-lane closures on eastbound and westbound I-70 near Colfax Avenue, Monday through Saturday, may be in place through the end of April. 
-Intermittent lane closures in the DDI may be required later this summer for final construction activities.

For more information on this project, visit the project webpage.


CDOT Road Construction Updates

View weekly construction updates from the Colorado Department of Transportation. 

Americans with Disability Act (ADA) improvement project begins on Colorado Highway 83 in early April

The Colorado Department of Transportation and prime contractor Chatos Concrete LLC, began an ADA sidewalk and curb ramp improvement project on April 6 along Colorado Highway 83 (Parker Road). Work is taking place at over 25 intersection locations between East Florida and East Quincy Avenue, Mile Points 68.8 to 74. The project is expected to be completed by July 2026.

Work will consist of removing and replacing concrete sidewalks and curb ramps at intersections throughout the project corridor, focusing on over 100 ramps that require upgrades to meet Americans with Disabilities Act (ADA) standards. Additional operations will include minor signage improvements, striping work, and push button enhancements.

Visit the project webpage for more information.

Travel Impacts
-Daytime work hours range from 7 a.m. to 7 p.m., Monday through Friday with additional work expected most Saturdays
-Nighttime work may be required intermittently throughout the project
-Lane closure times will vary depending on the location and direction of the highway
-Motorists can anticipate various single-lane and shoulder closures throughout the project corridor. All lane closures will be concentrated around intersection locations\
-East and westbound roads that intersect with CO 83 within the work zone may experience minor travel impacts
-Partial closures at the on and off-ramps of CO 83 and I-225 are expected intermittently. Though full ramp closures and detour routes are not anticipated, they may be required
-Sidewalk and crosswalk access will remain open for the duration of the project. Partial closures will be marked with signage to navigate around active construction areas
-Visit COTrip.org for real-time lane closure updates and road conditions on this project and others throughout the state.


ARTA I-70 Aerotropolis Parkway Interchange Project

The Aerotropolis Regional Transportation Authority and contract partner, Ames Construction, is constructing the I-70 Aerotropolis Parkway Interchange in Adams County.

Part of ARTA’s planned regional transportation infrastructure improvements across the district, the purpose of the project is to provide much-needed access to developments from Aurora and Adams County, and to improve connectivity to Denver International Airport and the adjacent area served by the Aerotropolis Regional Transportation Authority.

Visit the ARTA website for schedule and working hours and ongoing traffic impacts. For questions, call the project hotline at 720.388.2660 or email [email protected].


E-470 Road Widening Updates

View more on this project from the E-470 Tollway Authority.


East Colfax Bus Rapid Transit coming to Aurora

East Colfax BRT Construction will extend into Aurora in May 2026, from Yosemite to I-225:
Construction will be completed in a single phase, with work occurring simultaneously at both eastbound and westbound stations.
Traffic control cones and lane closures will be used in active construction zones as work progresses.
Traffic will remain open in the center lanes of East Colfax Ave. throughout the project.
Work will progress block by block, with each section expected to take about 3 to 6 months to complete.
Construction work for the side-running stations will occur within designated work zones that include portions of the sidewalk.

In progress:

Both directions of Colfax Avenue at Havana Street will have lane closures around the clock through June 22 due to the installation of new infrastructure related to the East Colfax Bus Rapid Transit Project.

The BRT project continues the work started in Denver to replace the existing 15 and 15L buses and save bus riders up to 30 minutes in travel time from Union Station to the R Line Station at I-225.

Watch the Colfax BRT series, Col-FAQS: On the Street.

More information—including a small business toolkit with resources for how to thrive during construction—is available at DenverGov.org/ColfaxBRT. Business owners also may take a self-assessment to consider how your business might be impacted by construction and what you may need to do to prepare. Additional resources are available from the Aurora South Metro Small Business Development Center (SBDC) at AuroraGov.org/SBDC.


ArapaGO: Transit Connections Plan Regional Meeting
Wednesday, May 20, 5 to 7 p.m., Aurora Central Library, 14949 E. Alameda Parkway
Learn more about what Arapahoe County is exploring related to on-demand transit, bike and e-bike access, scooters and more to improve everyday travel.
Registration is requested by Wednesday, May 6, to attend: https://bit.ly/42nrVzt
Learn more about the project at ArapahoeCO.gov/ArapaGO

 

TRAFFIC: Due to unforeseen circumstances, detours will remain in place on n-bound Gun Club Rd through the pm rush hour & into the evening for work at this site. We'll also need to continue work tmrrow, so detours will be in effect from 8:30am-mid afternoon.

TRAFFIC: Due to unforeseen circumstances, detours will remain in place on n-bound Gun Club Rd through the pm rush hour & into the evening for work at this site. We'll also need to continue work tmrrow, so detours will be in effect from 8:30am-mid afternoon.

City of Aurora | All Rights Reserved | Powered by CivicLive | © 2026 Civiclive.